REFERENCE PROJECTS SCOPE OF WORK
RELIEF SYSTEM VERIFICATION
PTG, GAS TREATMENT PLANT, CHARCO BAYO FIELD, ENTRE LOMAS AREA
END CUSTOMER: ACONCAGUA ENERGY, ARGENTINA
PROCESS ENGINEERING, FEED
- CALCULATION OF NEW PSV PSE-403
- CALCULATION REPORT, VERIFICATION OF RELIEF SYSTEM.
EXPANSION OF CRUDE OIL AND GAS TREATMENT PLANT
PTC - PTG LOS BASTOS “LBAS”
END CUSTOMER: TECPETROL
PROCESS ENGINEERING, FEED
- CALC. REPORT—SALINITY ANALYSIS
- CALC. REPORT—WATER STORAGE TANK
- CALC. REPORT—MULTIPHASE HEATER
- CALC. REPORT—DISPATCH PUMPS
- CALC. REPORT—PTG RELIEF SYSTEM
- CALC. REPORT—FUEL GAS SYSTEM
- PTC OPERATION MANUAL
- PTG OPERATION MANUAL
H2 COMPRESSORS, NHT UNIT.
(60+ DOC.)
NEW COMPRESSORS NH-C-002 A/B, KOD, HEAT EXCHANGER
END CUSTOMER: AXION ENERGY, CAMPANA REFINERY, ARGENTINA
FEED
- PROCESS
- ELECTRICAL
- INSTRUMENTATION
- BILL OF MATERIAL FOR CAPEX ESTIMATION
INSTRUMENTATION:
DESCRIPTIVE MEMORY OF THE INSTRUMENTATION AND CONTROL INSTALLATION
LIST OF INSTRUMENTS
LIST OF SIGNS
CONTROL AND SELF-REGULATING VALVES DATA SHEET
ON-OFF VALVES DATA SHEET
SAFETY VALVES DATA SHEET
FLOWMETER DATA SHEET
PRIMARY FLOW ELEMENTS DATA SHEET
TEMPERATURE INSTRUMENTS DATA SHEET
LEVEL INSTRUMENTS DATA SHEET
PRESSURE INSTRUMENTS DATA SHEET
F&G DATA SHEET
COUNT OF CABLES AND ELECTRICAL INSTALLATION MATERIALS
LOCATION PLANE AND INSTRUMENT CABLE CHANNELS
LAY OUT OF INSTRUMENT IMPLEMENTATION, PASSAGE BOXES/FIELD PANELS/F&G
INSTRUMENT CABLE LIST
REQUIREMENT FOR CONTROL AND SELF-REGULATING VALVES
ON-OFF VALVES REQUIREMENT
SAFETY VALVES REQUIREMENT
FLOWMETER REQUIREMENTS
REQUISITION OF PRIMARY FLOW ELEMENTS
REQUIREMENT OF TEMPERATURE INSTRUMENTS
REQUISITION OF LEVEL INSTRUMENTS
REQUISITION OF PRESSURE INSTRUMENTS
REQUISITION OF F&G INSTRUMENTS
REQUISITION/TRANSMITTERS OF OTHER INSTRUMENTS
INSTRUMENT CABLES REQUIREMENT
ELECTRICAL MATERIALS REQUIREMENT
REQUISITION OF MECHANICAL MATERIALS
COMPUTATION OF MECHANICAL INSTALLATION MATERIALS, INCLUDING SUPPORTS
COMPUTATION OF QUANTITIES AND TASKS FOR CAPEX BUDGET
PROCESS:
CALCULATION MEMORY - HOLE PLATES AND RESTRICTION HOLES
CALCULATION MEMORY - CONTROL VALVES
CALCULATION MEMORY - PRESSURE RELIEF DEVICES
ELECTRICAL:
MOTOR STARTING STUDY
DESCRIPTIVE MEMORY OF THE ELECTRICAL INSTALLATION
LOW VOLTAGE SINGLE-FILE DIAGRAMS
MEDIUM VOLTAGE SINGLE LINE DIAGRAMS
ELECTRICAL EQUIPMENT DATA SHEETS
REQUISITION OF ELECTRICAL EQUIPMENT
LOAD LIST
LOAD BALANCE
SE/ELECTRICAL ROOM LAYOUT (DASHBOARD SURVEY)
MC CABLES
CABLE LIST
ELECTRICAL CHANNELS DRAWING
LIST OF ELECTRICAL MATERIALS
MATERIAL REQUIREMENTS - ELECTRICAL MATERIALS
SE VERIFICATION TECHNICAL REPORT
LOAD FLOW STUDY AND ICC
TECHNICAL SPECIFICATION OF AUTOMATIC SWITCH
SOFT STARTER TECHNICAL SPECIFICATION
CIRCUIT SWITCH REQUIREMENT
CLASSIFICATION OF HAZARDOUS AREAS KNHF PLANT – LAYOUT
CLASSIFICATION OF HAZARDOUS AREAS KNHF PLANT – ELEVATION
COMPUTATION OF QUANTITIES AND TASKS FOR CAPEX BUDGET
CRUDE OIL PIPELINE.
LINDERO ATRAVESADO—CENTENARIO:
END CUSTOMER: PAN AMERICAN ENERGY, ARGENTINA
- DETAIL ENGINEERING◦ C/E MATRIX
- P&ID CRUDE OIL INDIRECT HEATER
- LACT UNIT PID
- CONTROL LOGIC & INTERLOCKS
- OPERATING MANUAL
- OPERATING AND CONTROL PHILOSOPHY
GAS PIPELINE “GPNK”.
CUSTODY MEASUREMENT AND CONDITIONING UNITS:
END CUSTOMER: ENARSA , ARGENTINA.
- DETAIL ENGINEERING
- MERCEDES-CARDALES DUCT
- CUSTODY FLOW RATE MEASUREMENT, FILTERS, SEPARATORS, SCRAPPERS TRAPS, REGULATION SKIDS
- PROCESS SIMULATION
- P&IDS UPDATE
- CONTROL VALVES AND RO CALCULATION
- PROCESS DELIVERABLES
- DATASHEETS
NEW HEATING PUMP.
PHOSPHATE AND DEGREASING SYSTEM
END CUSTOMER: TOYOTA, ARGENTINA
- FEED
- PROCESS SIMULATION
- P&ID
- MASS & ENERGY BALANCE
- HYDRAULIC CALCULATION
- DEFINITION OF MODEL OF PUMP AND HEATER
- DESCRIPTIVE REPORT
LITHIUM CARBONATE PLANT
LIME PLANT
CUSTOMER: EXAR MINERA, ARGENTINA
EXTENDED BASIC ENGINEERING
NEW TRANSFER PUMP
- INSTRUMENTATION
- CIVIL (CONCRETE)
- METAL STRUCTURES (SKID)
LITHIUM CARBONATE PLANT
LIME PLANT
CUSTOMER: EXAR MINERA, ARGENTINA
EXTENDED BASIC ENGINEERING
REPLACEMENT OF FLOCULANT PUMPS
- PROCESS ENGINEER
- MECHANICS
- ELECTRICITY
- INSTRUMENTATION
- METAL STRUCTURE (SKID)
LITHIUM CARBONATE PLANT
LIME PLANT
CUSTOMER: EXAR MINERA, ARGENTINA
EXTENDED BASIC ENGINEERING
NEW CIP WASHING UNIT
- PROCESS ENGINEER
- MECHANICS
- ELECTRICITY
- INSTRUMENTATION
- CIVIL (CONCRETE FOUNDATION)
- METAL STRUCTURE (SKID)
LITHIUM CARBONATE PLANT
SX PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
HYDRAULIC VERIFICATION FROM EST-1125 AND BBA-1128/9 TO CONSUMERS
- HYDRAULIC SIMULATION OF THE PROCESS
- VERIFICATION OF SPEED AND LOAD LOSS IN PIPELINES
- CHECKING SELECTED PUMPS (HEIGHT, FLOW, ANPA, POWER)
LITHIUM CARBONATE PLANT
ASH SODA PLAN
CUSTOMER: EXAR MINING, ARGENTINA
BASIC ELECTRICAL ENGINEERING
DOC UPDATE CCM 1305/ 1306 TO INSTALL NEW VFD FOR BBA-1025/6 PUMPS
- SINGLE-LINE DIAGRAM
- POWER DIAGRAM
- TOPOGRAPHIC PLAN
- FUNCTIONAL DIAGRAM
- TERMINAL BLOCK DIAGRAM
- LIST OF MATERIALS
LITHIUM CARBONATE PLANT
SX PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC ELECTRICAL ENGINEERING
DOC UPDATE CCM 1201/ 1202 TO INSTALL NEW COLUMN FOR BBA-1128/9 PUMPS.
- SINGLE-LINE DIAGRAM
- POWER DIAGRAM
- TOPOGRAPHICAL PLAN
- FUNCTIONAL DIAGRAM
- TERMINAL BLOCK DIAGRAM
- LIST OF MATERIALS
LITHIUM CARBONATE PLANT
REVERSE OSMOSIS PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
TAGGING OF EQUIPMENT AND INSTRUMENTS WITH EXAR NUMBERING
- LIST OF EQUIPMENT WITH EXAR TAG
- LIST OF INSTRUMENTS WITH TAG EXAR
- TAG UPDATE IN P&ID
PHOSPHATE AND DEGREASER SYSTEM
REVERSE OSMOSIS PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
VERIFICATION OF CAPACITY OF EQUIPMENT BEFORE INCREASE IN PRODUCTION
- OSMOSIS MEMBRANES
- HIGH AND LOW PRESSURE PUMPS
- BAG AND CARTRIDGE FILTER
- PIPES
- NEW EQUIPMENT DATA SHEET
- RECOMMENDATION REPORT
LITHIUM CARBONATE PLANT
CARBONATION REACTORS
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
PROPOSAL WITH NEW CONTROL SCHEME WITH RECYCLING
- SIMULATION OF THE PROCESS
- CONTROL PHILOSOPHY
- P&ID DIAGRAM
LITHIUM CARBONATE PLANT
ASH SODA PLAN
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
NEW PUMP BBA-1040/41 NEW CONTROL VALVE FV-9230A AND FLOWMETER FIT-6230
- HYDRAULIC CALCULATION
- CONTROL VALVE CALCULATION
- FLOWMETER DATA SHEET
- DATA SHEET V. CONTROL
LITHIUM CARBONATE PLANT
SX PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC ELECTRICAL ENGINEERING
ADJUSTMENT OF ELECTRICAL PROTECTION. DOC UPDATE CCM 1403 (SCHNEIDER) ON S.E.1401 TO INSTALL NEW COR PURIFICATION TAPE VFD.
- SINGLE-LINE DIAGRAM
- POWER DIAGRAM
- TOPOGRAPHIC PLAN
- FUNCTIONAL DIAGRAM
- TERMINAL BLOCK DIAGRAM
- LIST OF MATERIALS
LITHIUM CARBONATE PLANT
SX PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
DETERMINATION OF FLOWMETERS AND REGULATION VALVES IN THE 2ND PURIFICATION AND SX OUTPUT INTERCONNECTION.
- CONTROL PHILOSOPHY
- P&ID DIAGRAM
- FLOWMETER DATA SHEET
- REGULATING VALVES DATA SHEET
- LIST OF INSTRUMENTS, SIGNALS AND CABLES
LITHIUM CARBONATE PLANT
ASH SODA PLAN
CUSTOMER: EXAR MINING, ARGENTINA
BASIC ELECTRICAL ENGINEERING
PUMP PCLA-1035-BBS-1588. CCM-1305 UPGRADE (SCHNEIDER ELECTRIC)
- DOCUMENT DIGITIZATION FROM CCM (SCHNEIDER)
- ELECTRICAL CONDUITS
- LIST OF MATERIALS FOR ASSEMBLY AND PIPING
LITHIUM CARBONATE PLANT
ASH SODA PLAN
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
DETERMINE FLOWMETER AND REGULATION VALVE IN THE PEELER CENTRIFUGE INLET.
- DATA SHEET V. CONTROL
- MASS FLOWMETER DATA SHEET
LITHIUM CARBONATE PLANT
CARBONATION PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
SYST. BB MOTHER LIQUOR. OVERFLOW IN CENTRIFUGAL DISCHARGE.
- MASS BALANCE AND SIMULATION
- HYDRAULIC VERIFICATION OF PIPES
- P&ID DIAGRAM
- PUMP VERIFICATION
- BBAS AND V DATA SHEET. LOCK
- RECOMMENDATIONS REPORT
LITHIUM CARBONATE PLANT
CARBONATION PLANT
CUSTOMER: EXAR MINING, ARGENTINA
BASIC PROCESS ENGINEERING
RILES MODIFICATION. FAILURE IN CHECK VALVES. HYDRAULIC STUDY (WATER BLOW)
- MASS BALANCE
- HYDRAULIC VERIFICATION OF PIPES AND WATER HAMMER
- RECOMMENDATIONS REPORT
- PHILOSOPHY NEW CONTROL LEVEL REPLACEMENT VFD WITH CONTROL V.
- CHANGED PID
- DATA SHEET V. CONTROL
LITHIUM CARBONATE PLANT
PLANTA DE BORO
CUSTOMER: EXAR MINING, ARGENTINA
BASIC ENGINEERING PROCESSES & INSTRUM.
REPLACEMENT TKS HCL 32% BY GRP.
- CALCULATION AND HD V. OF PRESSURE/VACUUM
- TK INSTRUMENTS DATA SHEET
- INSTRUMENT CHANNELING
- LOOP DIAGRAM
- LIST OF MATERIALS
H2 COMPRESSORS, NHT UNIT
NEW COMPRESSORS NH-C-002 A/B, KOD, HEAT EXCHANGER
END CUSTOMER PAN AMERICAN ENERGY, CAMPANA REFINERY
ING. EXTENDED BASIC
- ING. OF PROCESSES
- ELECTRICAL ING.
- INSTRUMENTATION ENGINEER
- COMPUTATION OF QUANTITIES AND TASKS FOR CAPEX BUDGET